41st Street & I-29 Bridge
41st Street and Marion Road
41st Street and I-29
41st Street & I-29 Bridge
41st Street and Marion Road
41st Street and I-29
Traffic Alerts
7/2/2024
- All traffic control measures have been removed.
- Crews have completed painting underneath the bridge, and the I-29 lane closure has been removed.
- All painting and permanent pavement markings are completed.
- Crews have finished landscaping in all islands and medians.
Commuter Route Information
- The interchange is now a fully operational diverging diamond interchange (DDI), with all lanes of traffic open for motorists.
- Sidewalks and crosswalks across the 41st Street bridge are open for pedestrian use.
- Motorists are urged to use caution and follow painted traffic guidelines and signals to travel through the interchange.
Construction Progress
Construction began in early 2022 and was completed in summer 2024.
Click or tap on the dots to see more detail about a particular area.
South Side of 41st Street West of I-29 (2022)
Construction is complete on the south side of 41st Street west of I-29.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
Marion Road South of 41st Street (COMPLETE)
Construction is complete on Marion Road south of 41st Street.
North Side of 41st Street West of I-29 (2022)
Construction is complete on the north side of 41st Street west of I-29.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
Marion Road North of 41st Street (COMPLETE)
Construction is complete on Marion Road north of 41st Street.
South Side of 41st Street East of I-29 (2023)
Construction is complete on the south side of 41st Street east of I-29.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
North Side of 41st Street East of I-29 (2023)
Construction is copmlete on the north side of 41st Street east of I-29.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
Signal and Sidewalk at 38th St. (COMPLETE)
Construction at the intersection of 38th Street and Shirley Avenue is complete.
I-29 Interchange Bridge Work (2024)
Construction is complete on the I-29 bridge and interchange.
-
Removals
In ProgressCompleted -
Barrier Walls
In ProgressCompleted -
Drainage
In ProgressCompleted -
Electrical
In ProgressCompleted -
Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
I-29 Southbound Interchange Work (2022-2023)
Construction is complete on the Southbound I-29 interchange.
-
Removals
In ProgressCompleted -
Drainage & Sanitary Improvements
In ProgressCompleted -
Retaining Walls
In ProgressCompleted -
Winterize
In ProgressCompleted -
Removals
In ProgressCompleted -
West 41st off Ramp & I-29 West on Ramp
In ProgressCompleted -
Drainage & Sanitary Improvements
In ProgressCompleted -
East 41st St off Ramp & I-29 East on Ramp
In ProgressCompleted -
Electrical
In ProgressCompleted -
Medians
In ProgressCompleted -
Restoration
In ProgressCompleted
I-29 Northbound Interchange Work (2023)
Construction is complete on the Northbound I-29 interchange.
-
Removals
In ProgressCompleted -
Drainage & Sanitary Improvements
In ProgressCompleted -
Retaining Walls
In ProgressCompleted -
East 41st St off Ramp & I-29 East on Ramp
In ProgressCompleted -
West 41st St off Ramp & I-29 West on Ramp
In ProgressCompleted -
Electrical
In ProgressCompleted -
Medians
In ProgressCompleted -
Restoration
In ProgressCompleted
South side of 41st Street, East of I-29 (2024)
Construction is complete on the south side of 41st Street, east of I-29.
-
Removals
In ProgressCompleted -
Drainage
In ProgressCompleted -
Electrical
In ProgressCompleted -
Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
North side of 41st Street, West of I-29 (2024)
Construction is complete on the north side of 41st Street, west of I-29.
-
Removals
In ProgressCompleted -
Drainage
In ProgressCompleted -
Electrical
In ProgressCompleted -
Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
Carolyn Avenue (2024)
Construction is complete on Carolyn Avenue.
-
Retaining Walls
In ProgressCompleted -
Electrical
In ProgressCompleted -
Paving
In ProgressCompleted -
Restoration
In ProgressCompleted
-
April - November 2022
41st Street construction from Marion Road to Meadow Avenue (west half of project area)
-
April - November 2023
41st Street construction from Meadow Avenue to Shirley Avenue (east half of project area)
-
April - June 2024
Finishing touches and clean-up; complete construction