Traffic Alerts

March 20, 2023

41st Street, Interstate 29 to Shirley Avenue

  • Phase 2 construction of the 41st Street Diverging Diamond Interchange (DDI) project will kick off on Monday, March 27, 2023.
  • Crews will focus on the bridge structure and updates to 41st Street from Carolyn Avenue to Shirley Avenue. Work will begin first on the bridge, and traffic will be reduced to one lane open in each direction with a center turn lane across the bridge.
  • Road work on 41st Street will begin in late March, weather permitting. When road construction begins, the traffic pattern will change. One lane of traffic will remain open in both directions, with both east and westbound traffic on the south side of 41st Street from Terry Avenue to the bridge and from the bridge to East Empire Place.
  • When street construction begins, access to Carolyn Avenue from 41st Street will close permanently. Shops and businesses located on Carolyn Avenue can be accessed from the north via 38th Street or 34th Street. Signage will be in place to help guide motorists to Carolyn Avenue from 41st Street. Pedestrian access will be maintained on both sides of the bridge, but pedestrian through traffic along this section of 41st Street will be detoured to 26th Street or 49th Street.
  • Drivers are urged to use caution and reduce their speed while traveling through the construction area. Traffic control measures will be in place to guide motorists around all closures.

Construction Progress

Construction began in early 2022 and is anticipated to be completed in summer 2024. The project is divided into two phases: west and east. The west half of the project area includes 41st Street from Marion Road to Meadow Avenue. The east half includes 41st Street from Meadow Avenue to Shirley Avenue.

Click or tap on the dots to see more detail about a particular area.

Project overview map Completed South Side of 41st Street West of I-29 (2022)

South Side of 41st Street West of I-29 (2022)

Construction is complete on the south side of 41st Street west of I-29.

  • Removals

    In Progress
    Completed
  • Sanitary Sewer

    In Progress
    Completed
  • Water Main

    In Progress
    Completed
  • Drainage

    In Progress
    Completed
  • Grading

    In Progress
    Completed
  • Gravel

    In Progress
    Completed
  • Concrete Paving

    In Progress
    Completed
  • Misc Concrete

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
Completed Marion Road South of 41st Street (2022)

Marion Road South of 41st Street (COMPLETE)

Construction is complete on Marion Road south of 41st Street.

Completed North Side of 41st Street West of I-29 (2022)

North Side of 41st Street West of I-29 (2022)

Construction is complete on the north side of 41st Street west of I-29.

  • Removals

    In Progress
    Completed
  • Sanitary Sewer

    In Progress
    Completed
  • Water Main

    In Progress
    Completed
  • Drainage

    In Progress
    Completed
  • Grading

    In Progress
    Completed
  • Gravel

    In Progress
    Completed
  • Concrete Paving

    In Progress
    Completed
  • Misc Concrete

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
Completed Marion Road North of 41st Street (2022)

Marion Road North of 41st Street (COMPLETE)

Construction is complete on Marion Road north of 41st Street.

? South Side of 41st Street East of I-29 (2023)

South Side of 41st Street East of I-29 (2023)

Construction has not started on the south side of 41st Street east of I-29.

  • Removals

    In Progress
    Completed
  • Sanitary Sewer

    In Progress
    Completed
  • Water Main

    In Progress
    Completed
  • Drainage

    In Progress
    Completed
  • Grading

    In Progress
    Completed
  • Gravel

    In Progress
    Completed
  • Concrete Paving

    In Progress
    Completed
  • Misc Concrete

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
? North Side of 41st Street East of I-29 (2023)

North Side of 41st Street East of I-29 (2023)

Construction has not started on the north side of 41st Street east of I-29.

  • Removals

    In Progress
    Completed
  • Sanitary Sewer

    In Progress
    Completed
  • Water Main

    In Progress
    Completed
  • Drainage

    In Progress
    Completed
  • Grading

    In Progress
    Completed
  • Gravel

    In Progress
    Completed
  • Concrete Paving

    In Progress
    Completed
  • Misc Concrete

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
Completed Signal and Sidewalk at 38th St.

Signal and Sidewalk at 38th St. (COMPLETE)

Construction at the intersection of 38th Street and Shirley Avenue is complete.

? I-29 Interchange Bridge Work (2022-2023)

I-29 Interchange Bridge Work (2022-2023)

Construction is underway on the I-29 bridge and interchange.

  • Girders

    In Progress
    Completed
  • Southside Removals

    In Progress
    Completed
  • Southside Rehab & New Construction

    In Progress
    Completed
  • Northside Removals

    In Progress
    Completed
  • Northside Rehab & New Construction

    In Progress
    Completed
  • Electrical

    In Progress
    Completed
  • Closure Pour

    In Progress
    Completed
  • Barriers

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
? I-29 Southbound Interchange Work (2022-2023)

I-29 Southbound Interchange Work (2022-2023)

Construction is underway on the I-29 interchange.

  • Removals

    In Progress
    Completed
  • Drainage & Sanitary Improvements

    In Progress
    Completed
  • Retaining Walls

    In Progress
    Completed
  • Winterize

    In Progress
    Completed
  • Removals

    In Progress
    Completed
  • West 41st off Ramp & I-29 West on Ramp

    In Progress
    Completed
  • Drainage & Sanitary Improvements

    In Progress
    Completed
  • East 41st St off Ramp & I-29 East on Ramp

    In Progress
    Completed
  • Electrical

    In Progress
    Completed
  • Medians

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
? I-29 Northbound Interchange Work (2023)

I-29 Northbound Interchange Work (2023)

Construction has not started on the I-29 interchange.

  • Removals

    In Progress
    Completed
  • Drainage & Sanitary Improvements

    In Progress
    Completed
  • Retaining Walls

    In Progress
    Completed
  • East 41st St off Ramp & I-29 East on Ramp

    In Progress
    Completed
  • West 41st St off Ramp & I-29 West on Ramp

    In Progress
    Completed
  • Electrical

    In Progress
    Completed
  • Medians

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
  • April - November 2022

    41st Street construction from Marion Road to Meadow Avenue (west half of project area)

  • April - November 2023

    41st Street construction from Meadow Avenue to Shirley Avenue (east half of project area)

  • April - June 2024

    Finishing touches and clean-up; complete construction