Traffic Alerts

Recent Updates: 11/29

  • Light restoration and maintenance work will continue near the 41st Street northbound off-ramp at Interstate 29 (exit 77).
  • On Nov. 21, 2023, a sign bridge was installed north of 41st Street over the southbound lanes of Interstate 29.
  • Median landscaping work with isolated lane closures during the day will continue along 41st Street as weather allows.
  • Interstate 29 will stay reduced to two lanes while crews perform work on the berms under the 41st Street bridge.
  • The 41st Street interchange will be configured with standard intersections at the ramp ends for the winter. Lane configuration includes three lanes east and west of Interstate 29 with only two through lanes in each direction across the 41st Street bridge. A pedestrian zone is provided along the south edge of the bridge.
  • Construction will resume in spring 2024 to complete the diverging diamond configuration. More information about the DDI, including education for motorists, will be shared next spring ahead of the interchange fully opening as a DDI.

Commuter Route Information

  • A pedestrian route across the south side of the bridge is in place.
  • Northbound and southbound Interstate 29 is reduced to two lanes in each direction at the 41st Street interchange. The interstate lane closures will continue through December.
  • Motorists should be prepared for delays and use alternate routes during peak travel times. Drivers are urged to use caution and reduce their speed while traveling through the construction area. Traffic control measures are in place to guide motorists around all closures.

Motorists should be prepared for delays and use alternate routes during peak travel times. Drivers are urged to use caution and reduce their speed while traveling through the construction area.

Construction Progress

Construction began in early 2022 and is anticipated to be completed in summer 2024. The project is divided into two phases: west and east. The west half of the project area includes 41st Street from Marion Road to Meadow Avenue. The east half includes 41st Street from Meadow Avenue to Shirley Avenue.

Click or tap on the dots to see more detail about a particular area.

Project overview map Completed South Side of 41st Street West of I-29 (2022)

South Side of 41st Street West of I-29 (2022)

Construction is complete on the south side of 41st Street west of I-29.

  • Removals

    In Progress
    Completed
  • Sanitary Sewer

    In Progress
    Completed
  • Water Main

    In Progress
    Completed
  • Drainage

    In Progress
    Completed
  • Grading

    In Progress
    Completed
  • Gravel

    In Progress
    Completed
  • Concrete Paving

    In Progress
    Completed
  • Misc Concrete

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
Completed Marion Road South of 41st Street (2022)

Marion Road South of 41st Street (COMPLETE)

Construction is complete on Marion Road south of 41st Street.

Completed North Side of 41st Street West of I-29 (2022)

North Side of 41st Street West of I-29 (2022)

Construction is complete on the north side of 41st Street west of I-29.

  • Removals

    In Progress
    Completed
  • Sanitary Sewer

    In Progress
    Completed
  • Water Main

    In Progress
    Completed
  • Drainage

    In Progress
    Completed
  • Grading

    In Progress
    Completed
  • Gravel

    In Progress
    Completed
  • Concrete Paving

    In Progress
    Completed
  • Misc Concrete

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
Completed Marion Road North of 41st Street (2022)

Marion Road North of 41st Street (COMPLETE)

Construction is complete on Marion Road north of 41st Street.

Completed South Side of 41st Street East of I-29 (2023)

South Side of 41st Street East of I-29 (2023)

Construction is complete on the south side of 41st Street east of I-29.

  • Removals

    In Progress
    Completed
  • Sanitary Sewer

    In Progress
    Completed
  • Water Main

    In Progress
    Completed
  • Drainage

    In Progress
    Completed
  • Grading

    In Progress
    Completed
  • Gravel

    In Progress
    Completed
  • Concrete Paving

    In Progress
    Completed
  • Misc Concrete

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
Completed North Side of 41st Street East of I-29 (2023)

North Side of 41st Street East of I-29 (2023)

Construction is complete on the north side of 41st Street east of I-29.

  • Removals

    In Progress
    Completed
  • Sanitary Sewer

    In Progress
    Completed
  • Water Main

    In Progress
    Completed
  • Drainage

    In Progress
    Completed
  • Grading

    In Progress
    Completed
  • Gravel

    In Progress
    Completed
  • Concrete Paving

    In Progress
    Completed
  • Misc Concrete

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
Completed Signal and Sidewalk at 38th St.

Signal and Sidewalk at 38th St. (COMPLETE)

Construction at the intersection of 38th Street and Shirley Avenue is complete.

? I-29 Interchange Bridge Work (2022-2023)

I-29 Interchange Bridge Work (2022-2023)

Construction is underway on the I-29 bridge and interchange.

  • Girders

    In Progress
    Completed
  • Southside Removals

    In Progress
    Completed
  • Southside Rehab & New Construction

    In Progress
    Completed
  • Northside Removals

    In Progress
    Completed
  • Northside Rehab & New Construction

    In Progress
    Completed
  • Electrical

    In Progress
    Completed
  • Closure Pour

    In Progress
    Completed
  • Barriers

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
? I-29 Southbound Interchange Work (2022-2023)

I-29 Southbound Interchange Work (2022-2023)

Construction is underway on the I-29 interchange.

  • Removals

    In Progress
    Completed
  • Drainage & Sanitary Improvements

    In Progress
    Completed
  • Retaining Walls

    In Progress
    Completed
  • Winterize

    In Progress
    Completed
  • Removals

    In Progress
    Completed
  • West 41st off Ramp & I-29 West on Ramp

    In Progress
    Completed
  • Drainage & Sanitary Improvements

    In Progress
    Completed
  • East 41st St off Ramp & I-29 East on Ramp

    In Progress
    Completed
  • Electrical

    In Progress
    Completed
  • Medians

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
? I-29 Northbound Interchange Work (2023)

I-29 Northbound Interchange Work (2023)

Construction has not started on the I-29 interchange.

  • Removals

    In Progress
    Completed
  • Drainage & Sanitary Improvements

    In Progress
    Completed
  • Retaining Walls

    In Progress
    Completed
  • East 41st St off Ramp & I-29 East on Ramp

    In Progress
    Completed
  • West 41st St off Ramp & I-29 West on Ramp

    In Progress
    Completed
  • Electrical

    In Progress
    Completed
  • Medians

    In Progress
    Completed
  • Restoration

    In Progress
    Completed
  • April - November 2022

    41st Street construction from Marion Road to Meadow Avenue (west half of project area)

  • April - November 2023

    41st Street construction from Meadow Avenue to Shirley Avenue (east half of project area)

  • April - June 2024

    Finishing touches and clean-up; complete construction